Right on schedule for acceptance by our client …
In mid-2020, BDI entrusted us with a very exciting project; the construction of 30 tanks for a big project close to home. With 13 tanks in carbon steel, 17 tanks in stainless steel, a range from 3.3m to 15.2m in diameter and heights from 4.5 to 20m, this project offers a veritable smorgasbord of storage tank options. And to make matters even more interesting, we are building the 5 biggest tanks on-site at the client, some at Geldof and others on our construction site in Antwerp. At this moment, we have fully welded 3 tanks, nearly finished the other two and installed the off-site built tanks at the tank farm. After a few finishing touches, we will be right on schedule for acceptance by our client. We’d like to thank the entire team for their efforts so far, and wish them the best of luck for the remaining 2 tanks. To be continued…
15th of September, 2021