In the north of France, we are have nearly finished construction of a tank for the storage of Acrylonitril, as part of the bigger project, called WIMAP.
Geldof was responsible for the engineering, preparation, construction and protection of the carbon steel storage tank at the Ineos site in Wingles.
After engineering and preparation in our workshop were finished, everything was transported to its destination.
Once arrived, the tank was built on site and has also been painted.
The bottom and lower rings were placed directly on the foundations, while the upper ring and the roof were prepared next to the tank.
We used this method in order to save time and work as efficiently as possible.